6.24 Indonesia hadad 3:50 p.m to Jakarta airport local time to celigon hotel 7 PM. Chen, head of Indonesia Taiko. At eight o 'clock the next day started the Taiko Indonesia project equipment debugging. On June 25, with Taiko head for operation. A. preparation before starting the: 1. Check whether equipment installation according to the diagram construction. 2. Check whether equipment parts accessories device damage caused by installation. 3. Check the mechanical equipment lubrication if item has been completed lubrication added. 4. Check the insulation whether insulation in place. 5. Check the soft connection, active connection, sealing joint is dripping and leakage. 6. Check the power supply circuit is connected correctly, to zero separated from zero to one. Item 7. Electricity detection, need one by one to electricity, drive motor, drive in the normal transport, positive and negative to positive
|